Decking on Wilshire Bl at Gayley Av (Stage 2 of 4)
Metro contractors will continue decking for the Westwood/UCLA Station through November 2022. Decking on Wilshire Bl between Veteran Av and Westwood Av will be completed in approximately 14 weekends, requiring continuous work from 11pm Friday through 6am Monday. There will be temporary partial street closures implemented on Wilshire Bl in four stages. Traffic will be detoured around the construction work and notices updated weekly.
Decking is a process where the street is excavated at a depth of about 10 to 12 feet and deck beams are installed over the piles. Concrete precast deck panels are installed over the deck beams to create a temporary street surface for vehicles and pedestrian access. This work allows for construction activities to continue below the surface of Wilshire Bl and help reduce community impacts.
Remaining Dates for Stage 2 of Decking:
October 28 through October 31
Continuous work hours: 11pm on Friday through 6am on Monday
Preparation Work for traffic control: October 14 and 16, 9pm to 11pm
Traffic Control:
Stage 2: Anticipated 3 Weekends
• Traffic on Gayley Av will be restricted between Wilshire Bl and Lindbrook Dr. No northbound traffic on Gayley Av at Wilshire Bl. Access to buildings will be available with the support of flaggers.
• Northbound Midvale Av traffic will only be allowed to turn right to eastbound Wilshire Bl. Left turns from Midvale Av to Wilshire Bl will be restricted.
• Westbound traffic on Wilshire Bl will be restricted between Westwood Bl and Veteran Av.
• Westbound Wilshire Bl traffic lanes will be reduced between Malcolm Av and Westwood Bl.
• Westbound Wilshire Bl traffic will be closed at Westwood Bl. Traffic will be permitted to head northbound or southbound on Westwood Bl on the detour routes. Westbound traffic will be detoured to Ohio Av and Kinross Ave, and onto Veteran Ave.
• Eastbound Wilshire Bl traffic will be reduced to two traffic lanes between Veteran Av and about 50 feet east of Gayley Av. Reduced eastbound Wilshire Blvd lanes begin before Veteran Av through Westwood Bl.
• Left-hand and right-hand turns are accessible for eastbound Wilshire Blvd traffic onto Veteran Av and Westwood Bl.
• Southbound Westwood Bl may not turn right to westbound Wilshire Bl.
• Southbound Glendon Av may not turn right to westbound Wilshire Bl.
• Northbound Westwood Bl may not turn left to westbound Wilshire Bl.
• Westbound Lindbrook Dr may not turn left at Gayley Av.
• The northern sidewalk on Wilshire Bl between Gayley Av and Veteran Av remains closed. Pedestrian traffic will be detoured to use the southern sidewalk.
• The west and east leg crosswalks at the Wilshire Bl and Gayley Av intersection will be closed to Pedestrians. Crosswalks will not be closed simultaneously each weekend. There will be three crosswalks open at all times.
Noteworthy
• Access to driveways, residences & businesses will always be maintained unless there is prior notification of blocked access.
• Access for pedestrians will be maintained outside of construction zones.
• Access for the Fire Department and emergency responders will be maintained.
• Parking restrictions will be implemented in the immediate area of the work zone.
• Construction is dynamic and schedules are subject to change.
• 24/7 Hotline: 213-922-6934