Fox Hills Dr and Santa Monica Bl: Instrumentation InstallationSummaryMetro contractors will continue instrumentation installations in preparation for the Purple (D Line) Extension Project. Work will require temporary street closures from 9am to 3:30pm and 11pm to 6am. Streets will be restored once installations are complete. Instrumentation installations will be done on Missouri Av, Fox Hills Dr, and Santa Monica Bl.Scheduled Work Dates & Locations 1. Missouri Av and Fox Hills Dr Date: October 31 to December 16 Work Hours: Monday to Friday, 9am to 3:30pm 2. Santa Monica Bl, between Benecia Av and Comstock Av Date: October 31 to December 16
Work Hours: Monday to Friday, 9am to 3:30pm and 11pm to 6am
Noteworthy
Metro AccessMetro bus stops may be relocated, or lines could be impacted. For information changes to Metro service, please call 323.GoMetro. Passengers are encouraged to use the Transit App to plan their travels. |